Weekly Construction Updates

Archives

I-89 Bridges Project

I-89 Bridges Project
AOT Project No. IM 089-2(43)

Project Location: 
The I-89 Bridges Project is located at Exit 10 on I-89 in Waterbury.


I-89 Bridges NB Off-Ramp Bridge  

Paving on Stowe Street has been completed. Crews will continue to work in the Stowe Street Park laying additional top soil and planting trees this week without traffic impacts.  The two lanes on Stowe Street will be open to two-way traffic.

Damaged concrete repair on the piers on the northbound and southbound interstate bridges continues without impact to traffic.

No night and weekend work is anticipated this week. VTrans will keep you informed of any changes to construction activities related to the I-89 Bridges Project over the next few weeks

Waterbury Roundabout Project

AOT Project No: STP SGNL (18)

Project Location: Intersection of Routes 100/2 in Waterbury. 2016 work location is on US 2 east of the Roundabout. 

This project is complete. 

VT100 Duxbury - Culvert Project

Project Location:  VT 100 Bridge #193 in Duxbury over Crossett Brook

This project is complete. 

Route 2/Route 100 S Temporary Signal

AOT Project No. Waterbury Area STP WKZN (9) C/2

Project Location:  Southerly intersection of US 2/VT 100 S.

This project is complete. 

Stowe - VT 108 Bridge Reconstruction

AOT Project No. BRF 0235(1)

Project Location:  The VT 108 Bridge is located on VT 108 approximately 350 feet north of the intersection of VT 100 and VT 108 in Stowe. 

This project is complete.

Waitsfield-Moretown-Duxbury (VT 100 Preventive Maintenance Paving)

AOT Project No. STP SURF(39)

Project Location: The Waitsfield – Moretown – Duxbury VT 100 Preventive Maintenance Paving project limits begin 2.4 miles north of Warren/Waitsfield town line (Fiddlers Green) and extend to the intersection of US 2 in Moretown for a distance of 12 miles.

This project is complete.

Bolton-Waterbury (US 2 Reclaim) Project

AOT Project No: STP 2709(1)

Project Location: Route 2 - Parro's Gun Shop in Waterbury west along Route 2 to just beyond Latham Trailer Sales in Bolton. Estimated completion late October 2014.

This project is complete.

Northbound Off Ramp Signal Project

AOT Project No. NHG SGNL(43)

Project Location: Northbound Off Ramp is located at Exit 10 at intersection of I-89 and VT100.

This project is complete.

Please focus on safety when driving through the construction work zone and remember, it is now against the law to use a hand held cell phone in a construction work zone.

Contact Annabelle Dally, 802-825-2555, with questions.