Weekly Construction Updates

Archives

Waterbury-Stowe VT Route 100 Rehabilitation Project

Project: Waterbury – Stowe VT Route 100 Rehabilitation Project

Construction Update: May 18, 2018

Project Location:  VT 100 in the Towns of Waterbury and Stowe.

Please be Advised:

  • Expect travel delays along Route 100 between Waterbury and Stowe over the next several months while the road construction takes place. Surface conditions may vary as portions of the roadway may be milled or gravel. Please plan your travel accordingly and leave plenty of time while this necessary work occurs.
  • Beginning Sunday May 20, the drainage work in Stowe Lower Village will resume for the week. Excavation of the concrete slabs in Waterbury will continue from Stowebury Road to the north.

As of today, concrete slabs were removed and a new gravel roadbase was filled between Guptil Road and Stowebury Road. Milling has been completed to just south of Waterbury Center.

Next week, excavation of the concrete slabs in Waterbury will continue from Stowebury Road to the north. Paving is scheduled towards the end of the week for part of the segment where concrete removal has been completed.

Milling from Waterbury Center northward will resume in approximately two weeks.

Nighttime work is limited to the hours of 7 PM to 6 AM, Sunday through Thursday. During these hours, alternating one-way traffic will be implemented. Flaggers will be present to assist motorists through the work zones.

During daytime hours, two lanes of travel will remain open unless emergency situations warrant otherwise. This may result in minor traffic delays. No weekend work is anticipated this week. All work is weather permitting.

The Waterbury – Stowe VT 100 construction project will provide a complete rehabilitation of the 9.5-mile corridor between Waterbury and Stowe. The work requires concurrent construction activities with multiple crews for roadway rehabilitation and drainage work. This will result in potential travel delays and varying surface conditions along the route.

When you travel this stretch of roadway, you may encounter varying surface conditions in different locations from day to day, and night to night. Drivers should slow down, observe signage, and factor in extra travel time. Proceed with caution and be aware of other vehicles, large trucks, construction crews, and changing road conditions. Leave plenty of space between vehicles to avoid small stones and gravel that may get kicked-up.   

I-89 Bridges Project

AOT Project No. IM 089-2(43)

Project Location: 
The I-89 Bridges Project is located at Exit 10 on I-89 in Waterbury.

 
This Project is complete.

Waterbury Roundabout Project

AOT Project No: STP SGNL (18)

Project Location: Intersection of Routes 100/2 in Waterbury. 2016 work location is on US 2 east of the Roundabout. 

This project is complete. 

VT100 Duxbury - Culvert Project

Project Location:  VT 100 Bridge #193 in Duxbury over Crossett Brook

This project is complete. 

Route 2/Route 100 S Temporary Signal

AOT Project No. Waterbury Area STP WKZN (9) C/2

Project Location:  Southerly intersection of US 2/VT 100 S.

This project is complete. 

Stowe - VT 108 Bridge Reconstruction

AOT Project No. BRF 0235(1)

Project Location:  The VT 108 Bridge is located on VT 108 approximately 350 feet north of the intersection of VT 100 and VT 108 in Stowe. 

This project is complete.

Waitsfield-Moretown-Duxbury (VT 100 Preventive Maintenance Paving)

AOT Project No. STP SURF(39)

Project Location: The Waitsfield – Moretown – Duxbury VT 100 Preventive Maintenance Paving project limits begin 2.4 miles north of Warren/Waitsfield town line (Fiddlers Green) and extend to the intersection of US 2 in Moretown for a distance of 12 miles.

This project is complete.

Bolton-Waterbury (US 2 Reclaim) Project

AOT Project No: STP 2709(1)

Project Location: Route 2 - Parro's Gun Shop in Waterbury west along Route 2 to just beyond Latham Trailer Sales in Bolton. Estimated completion late October 2014.

This project is complete.

Northbound Off Ramp Signal Project

AOT Project No. NHG SGNL(43)

Project Location: Northbound Off Ramp is located at Exit 10 at intersection of I-89 and VT100.

This project is complete.

Please focus on safety when driving through the construction work zone and remember, it is now against the law to use a hand held cell phone in a construction work zone.

Call the project hotline 802-496-3376, with questions.