Weekly Construction Updates

Archives

Waterbury - Stowe VT Route 100 Rehabilitation Project

CONSTRUCTION UPDATE: May 17, 2019

PROJECT TYPE:  Roadway Rehabiliation

PROJECT LOCATION:  VT 100 in the Towns of Waterbury and Stowe.

TRAFFIC IMPACT: Two-way traffic will be maintained during daytime hours. Minor travel impacts are possible and include potential stoppages and/or intermittent periods of alternating one-way traffic patterns. During evening hours, alternating one-way traffic and lane closures are expected along Route 100. Flaggers will be on site to assist motorists through the work zone.

DURATION: The day work scheduled to occur Monday through Friday, will have minimal traffic impacts between the hours of 7AM and 7PM. The night work scheduled to occur Sunday through Friday, will require lane closures along Route 100 between the hours of 7PM and 7AM.

PROJECT COMPLETION: October 2019

SPECIAL CIRCUMSTANCES/NOTICES:  Next week, crews will continue working on the new signals at the intersections along Route 100 between Blush Hill Road and Guptil Road during the day, weather permitting. The signal work will occur outside of the roadway with little to no impact to traffic.

Crews will continue work on the sidewalk in Stowe. The sidewalk includes the east side of Route 100 between Sylvan Park Road and Thomas Lane and the west side of Route 100 between Thomas Lane and River Road. Crews will be excavating the area at night between 7PM and 7AM and constructing the curb and sidewalk between the hours of 7AM and 7PM. In addition, crews will continue work regrading the existing bike path along the west side of Route 100 beginning north of River Road.

Throughout the week, crews will continue making repairs to drainage piping and complete slope work by laying stone at driveways along Route 100.

Chirpers are now installed to replace the back-up alarms on all equipment in the lower village and saw cutting has been rescheduled to occur during the daytime to help mitigate nighttime noise levels.

I-89 Bridges Project

AOT Project No. IM 089-2(43)

Project Location: 
The I-89 Bridges Project is located at Exit 10 on I-89 in Waterbury.

 
This Project is complete.

Waterbury Roundabout Project

AOT Project No: STP SGNL (18)

Project Location: Intersection of Routes 100/2 in Waterbury. 2016 work location is on US 2 east of the Roundabout. 

This project is complete. 

VT100 Duxbury - Culvert Project

Project Location:  VT 100 Bridge #193 in Duxbury over Crossett Brook

This project is complete. 

Route 2/Route 100 S Temporary Signal

AOT Project No. Waterbury Area STP WKZN (9) C/2

Project Location:  Southerly intersection of US 2/VT 100 S.

This project is complete. 

Stowe - VT 108 Bridge Reconstruction

AOT Project No. BRF 0235(1)

Project Location:  The VT 108 Bridge is located on VT 108 approximately 350 feet north of the intersection of VT 100 and VT 108 in Stowe. 

This project is complete.

Waitsfield-Moretown-Duxbury (VT 100 Preventive Maintenance Paving)

AOT Project No. STP SURF(39)

Project Location: The Waitsfield – Moretown – Duxbury VT 100 Preventive Maintenance Paving project limits begin 2.4 miles north of Warren/Waitsfield town line (Fiddlers Green) and extend to the intersection of US 2 in Moretown for a distance of 12 miles.

This project is complete.

Bolton-Waterbury (US 2 Reclaim) Project

AOT Project No: STP 2709(1)

Project Location: Route 2 - Parro's Gun Shop in Waterbury west along Route 2 to just beyond Latham Trailer Sales in Bolton. Estimated completion late October 2014.

This project is complete.

Northbound Off Ramp Signal Project

AOT Project No. NHG SGNL(43)

Project Location: Northbound Off Ramp is located at Exit 10 at intersection of I-89 and VT100.

This project is complete.

Please focus on safety when driving through the construction work zone and remember, it is now against the law to use a hand held cell phone in a construction work zone.

Call the project hotline 802-496-3376, with questions.