Weekly Construction Updates

Archives

Waterbury - Stowe VT Route 100 Rehabilitation Project

Construction Update: October 18, 2018

Project Location:  VT 100 in the Towns of Waterbury and Stowe.

Due to the inclement weather anticipated next week, the crew will be paving on Route 100 on Friday, October 19 beginning at 7 PM and will be off the road by 6 AM Saturday, October 20.

There is approximately 1 mile of Route 100 between Moscow Road and just south of Gold Brook Road remaining to receive a second lift pavement. Many of the side road aprons have been paved heading south from Stowe and the remainder are anticipated to be completed throughout next week.

Private driveway aprons will be paved before the construction team moves out for winter. All work for the 2018 construction season is expected to be completed in advance of the Thanksgiving Holiday. The crew will return in the Spring to complete the final lift of pavement from just north of the roundabout in Waterbury to the Safety Complex in Stowe.

Paving: Friday, October 19, the paving crew will continue to pave a second lift of asphalt to complete paving operations on the Route 100 mainline between Moscow Road and just south of Gold Brook Road. Paving operation will then continue Sunday, October 21 on side road aprons. Once paving on Route 100 and all side road aprons have been completed, the crew will begin private drive aprons. All paving operations are weather dependent.

Guardrail/Shoulders: Guardrail installation operations will resume Sunday night along Route 100 in Stowe, continuing south towards Waterbury. Crews will also continue clean-up of the road shoulders, backup new pavement, and complete stone ditching and slope work throughout the week.

Traffic: Motorists may encounter several areas of one-way alternating traffic along the construction route to facilitate road, guardrail, shoulder, drive and side road apron work.

Flaggers will be present to assist motorists through the work zones. This may result in minor traffic delays. All work is weather permitting.
 

I-89 Bridges Project

AOT Project No. IM 089-2(43)

Project Location: 
The I-89 Bridges Project is located at Exit 10 on I-89 in Waterbury.

 
This Project is complete.

Waterbury Roundabout Project

AOT Project No: STP SGNL (18)

Project Location: Intersection of Routes 100/2 in Waterbury. 2016 work location is on US 2 east of the Roundabout. 

This project is complete. 

VT100 Duxbury - Culvert Project

Project Location:  VT 100 Bridge #193 in Duxbury over Crossett Brook

This project is complete. 

Route 2/Route 100 S Temporary Signal

AOT Project No. Waterbury Area STP WKZN (9) C/2

Project Location:  Southerly intersection of US 2/VT 100 S.

This project is complete. 

Stowe - VT 108 Bridge Reconstruction

AOT Project No. BRF 0235(1)

Project Location:  The VT 108 Bridge is located on VT 108 approximately 350 feet north of the intersection of VT 100 and VT 108 in Stowe. 

This project is complete.

Waitsfield-Moretown-Duxbury (VT 100 Preventive Maintenance Paving)

AOT Project No. STP SURF(39)

Project Location: The Waitsfield – Moretown – Duxbury VT 100 Preventive Maintenance Paving project limits begin 2.4 miles north of Warren/Waitsfield town line (Fiddlers Green) and extend to the intersection of US 2 in Moretown for a distance of 12 miles.

This project is complete.

Bolton-Waterbury (US 2 Reclaim) Project

AOT Project No: STP 2709(1)

Project Location: Route 2 - Parro's Gun Shop in Waterbury west along Route 2 to just beyond Latham Trailer Sales in Bolton. Estimated completion late October 2014.

This project is complete.

Northbound Off Ramp Signal Project

AOT Project No. NHG SGNL(43)

Project Location: Northbound Off Ramp is located at Exit 10 at intersection of I-89 and VT100.

This project is complete.

Please focus on safety when driving through the construction work zone and remember, it is now against the law to use a hand held cell phone in a construction work zone.

Call the project hotline 802-496-3376, with questions.